Vogtle delays and cost overruns not our fault, Georgia Power CEO says


Years of delays and billions of cost overruns at Plant Vogtle cannot be blamed on any mistakes made by Georgia Power, the company’s chief executive said in an interview Friday.

In a meeting with reporters at The Atlanta Journal-Constitution, Paul Bowers cited other factors, including bankruptcy of the main contractor, as well as actions and requirements imposed by the Nuclear Regulatory Commission.

Has Georgia Power made mistakes?

“The answer to that question is no,” Bowers said.

Now, there are more costs projected for Vogtle. In recent days, the utility, a unit of Southern Co., has appeared at hearings of the Georgia Public Service Commission to argue that commissioners agree to let the company pass along to customers those new costs – potentially, billions of dollars over the life of the plant.

Bowers said he does not expect any further significant overruns beyond that. But if there are, he said he would ask the PSC to let the company pass along those costs to customers as well.

He told the AJC that Georgia Power would seek “all prudently incurred costs on the project.”

The second of the two units under construction is now scheduled for completion in late 2022, a year after the first unit, according to Georgia Power.

“We have confidence that this is going to be met,” Bowers said Friday of the new schedule and cost.

The project has repeatedly missed goals in the past and has long been contested by watchdog groups. Vogtle was years behind schedule and over-budget even before Westinghouse filed for bankruptcy earlier this year.

While Bowers said at least some delays were connected to the NRC, two years ago, Georgia Power’s then-executive vice president for nuclear development said NRC regulatory changes had no significant impact on the project’s time-table.

Opponents of the project appearing at the PSC hearings this week argued that Georgia Power should not be permitted to pass the charges on to customers.

The commissioners will in February decide whether to give a nod to continue with the project and allow the company to pass new costs along to customers.

Bowers said Friday that nuclear power now provides “19 or 20” percent of the electricity produced for the state by Georgia Power. The addition of Vogtle would add only incrementally to that, bringing nuclear’s share to 21 or 22 percent of the total.

Despite that relatively small difference, nuclear power has the advantage of reliability and – unlike some renewable energy sources – is always “on.”

Coal now accounts for less than 30 percent of the power produced, he said. Moving even further away from coal protects the state from whatever environmental restrictions might be imposed in the future, he said.

He also dismissed the idea that the decline of coal will reverse and the product might once again become a competitive source of power.

“Economics drive all the decisions,” he said. “Coal just can’t compete.”

Anastaciah Ondieki contributed to this story

MYAJC.COM: REAL JOURNALISM. REAL LOCAL IMPACT.

AJC Business reporter Michael E. Kanell keeps you updated on the latest news about jobs, housing and consumer issues in metro Atlanta and beyond. You'll find more on myAJC.com, including these stories:

Never miss a minute of what's happening in local business news. Subscribe to myAJC.com. 



Reader Comments ...


Next Up in Business

Is active or passive investing best? You may be surprised
Is active or passive investing best? You may be surprised

It’s hard to believe, but we’re more than halfway through 2018. So far, it’s been a year of market ups and downs. We’ve endured a correction, experienced a rebound, and are now back closer to flat. The recent choppiness makes this a good time to revisit the great debate between active and passive investing. Last year, an email...
Atlanta company eyeing sports betting industry outside Georgia
Atlanta company eyeing sports betting industry outside Georgia

When Inside Injuries launched in 2016, the company was intended to supply fantasy sports players and companies with injury analysis on top players across sports, CEO Tracy Hankin said. Sports betting wasn’t in the company’s sights. A Supreme Court ruling in May, which struck down a federal law outlawing sports betting outside of Nevada...
No, you don’t need a perfect score to be an exceptional borrower

WASHINGTON — I have been told many times that I’m a perfectionist, but I feel that I’m not perfect enough for such a label. Yet it’s true that my life is driven by a relentless report-card-like quest for excellence. This is why I understand people with super-high FICO credit scores who seethe that they have yet to get a perfect...
Man fired after encounter with 'racist' customer. After sharing story, Home Depot offers job back.
Man fired after encounter with 'racist' customer. After sharing story, Home Depot offers job back.

After a man last Thursday approached the checkout at a Home Depot in Albany, New York, staff member Maurice Rucker asked him to leash his dog. That's when the man exploded. » RELATED: Atlanta's Home Depot growing in various ways, but not new stores Rucker, a 60-year-old black man, claimed he was fired Tuesday after defending himself from...
Peach problem: Georgia fruits clobbered again
Peach problem: Georgia fruits clobbered again

Uncooperative weather has taken a jumbo bite out of the Peach State’s peach crop , a second year of pain for growers of the iconic fruit. And similar hardship appears to have eliminated half Georgia’s more lucrative blueberry yield. The difficult years have left Atlanta shoppers in the produce aisle facing the prospect of paying...
More Stories