Mercedes-Benz Stadium falls behind schedule

AJC exclusive: Target for opening pushed back to June 1, 2017, affecting new soccer team


Construction of the downtown stadium that will become home to the Atlanta Falcons and a new professional soccer team won’t be completed in time for a long-planned March 2017 opening.

The new target date for completion of Mercedes-Benz Stadium is June 1, 2017, Arthur Blank, owner of the Falcons and Major League Soccer team Atlanta United, told The Atlanta Journal-Constitution in an interview Thursday.

Blank attributed the delay to the design process for the steel structure that will support the stadium’s complex retractable roof and massive video board.

He said the delay will add to the cost of the $1.4 billion project but declined to say how much. He said he’ll bear the additional cost, as required by his stadium deal with the city and state.

If the new target date is achieved, the stadium would still open in time for the start of the Falcons’ planned first season there. NFL exhibition games are played in August, and the regular season opens in September.

But the delay means Blank’s soccer team won’t have use of its home stadium for the first three months of the 2017 season, slated to be Atlanta United’s debut season. MLS teams’ 34-game schedules run from early March until late October.

Blank said Atlanta United remains committed to beginning play in 2017 and “fully anticipates” playing all 17 of its home games in the new stadium that season, meaning it would play on the road through the first three months of the schedule. But he said an alternate temporary venue will be lined up in Atlanta for the soccer team if needed, with a decision on that possibility coming later this year.

Construction of the 71,000-seat Mercedes-Benz Stadium began in early 2014 and continues with as many as 1,400 workers on site daily. The delay stems from two of the stadium’s signature features: an eight-piece retractable roof that is supposed to open and close in seven minutes and a 58-foot-high oval video board incorporated into the roof opening.

Challenges in completing the design of the steel structure for the roof and video board have backed up the project and are the primary factors in revising the target date for completion, Blank said.

“It’s a complex building,” he said. “Particularly, the steel is complicated; the roof is complicated; the halo scoreboard is complicated. The design drawings leading up to fabrication and eventually erection (of the steel structure) took longer than anybody expected because of the complexity.”

Blank said progress is being made on those designs by lead architect HOK and its subcontractors.

Steel work continued at the construction site Thursday. Blank said placement of steel for the roof will accelerate in the spring. In the end, he said, the roof and video board will look and function as shown in the renderings that have been released publicly.

“There will be no compromise at all,” he said. “It’s going to be a unique, one-of-a-kind stadium.”

Although Blank said he has “absolutely zero doubt” that the Falcons will open the 2017 season in the stadium and that college-football events will be played as scheduled in the building that season, this delay leaves relatively little margin in the timeline for further problems.

The delay will require “compressing” more work into less time on the job site later this year, Blank said.

“What happens is … (subcontractors) have to work double-time, triple-time, whatever it may be,” he said. That will result in additional costs, which Blank said he has agreed to pay, although “I don’t know what the final numbers will be.” All cost overruns are the Falcons’ responsibility, according to the stadium deal.

“That is risk I assumed going into the project and one that I’m supporting,” Blank said.

The stadium deal called for $200 million in proceeds from bonds backed by Atlanta hotel-motel taxes to go toward stadium construction, with hundreds of millions of additional hotel-motel tax dollars — the exact amount depending on tax collections — going toward costs of financing, operating and maintaining the stadium over 30 years.

The Georgia Dome, the Falcons’ current home, is scheduled to be demolished before the start of the 2017 football season, provided the new stadium is on track for completion.

A Major League Soccer executive said Thursday the league is aware of the delay and not alarmed by it.

“MLS has extensive experience working collaboratively with our clubs on scheduling when dealing with delays on new stadiums,” Dan Courtemanche, the league’s executive vice president of communications, said. “In fact, only one club, (New York) Red Bulls in 2010, played their opening match in their new stadium. Most clubs went four-eight weeks on the road before their home opener when playing in a new venue. … Other clubs played in temporary venues.”

He cited seven examples of teams that opened new stadiums at least three months into a season.

“For us, it’s business as usual,” Courtemanche said of the Atlanta delay.


Reader Comments ...


Next Up in Atlanta Falcons

The Falcons roster: Should they stay or go? 
The Falcons roster: Should they stay or go? 

Two yards away. The Falcons were just two yards away from advancing to their second consecutive NFC championship this season. After finishing 11-7 overall, it was just the third time in franchise history that teams posted back-to-back 10-win seasons. After the past two seasons, they join coach Mike Smith’s teams from 2010-12 that did it three...
Early mock drafts: Massive Vita Vea headed to Falcons
Early mock drafts: Massive Vita Vea headed to Falcons
Washington defensive tackle Vita Vea, who’s 6-foot-5 and 340 pounds, is a popular pick for the Falcons in some pre-combine mock drafts. At this juncture in the offseason, Vea makes sense because the Falcons may not be able to re-sign defensive tackle Dontari Poe. Poe played last season on an incentive-laden $8 million contract. His market value...
10 key offseason dates for Atlanta Falcons
10 key offseason dates for Atlanta Falcons

The Atlanta Falcons have a number offseason priorities, among them singing quarterback Matt Ryan to a team-friendly long-term deal. Here are 10 key dates to know about as the team heads into the 2018 offseason. The NFL Scouting Combine takes place in Indianapolis. Head coach Dan Quinn and general manager Thomas Dimitroff will be among the Falcons officials...
Falcons hire Parmalee as running backs coach, two other assistants  
Falcons hire Parmalee as running backs coach, two other assistants  

The Falcons hired former NFL running back Bernie Parmalee as their running backs coach on Wednesday. Parmalee replaces Keith Carter, who left to become the Titans running backs coach earlier this offseason. The team also hired Mayur Chaudhari as a special teams assistant and Chad Walker as an offensive assistant.  “We are excited to be able...
Cover 9@9: Ryan set to become NFL’s first $30 million dollar a year man 
Cover 9@9: Ryan set to become NFL’s first $30 million dollar a year man 
1. $30 million man. Falcons quarterback Matt Ryan is in line to become the NFL’s first $30 million a year man.  “It’s quite possible,” Joel Corry, CBS Sports NFL business analyst told The Atlanta Journal-Constitution on Tuesday. “Kirk Cousins might beat him to it, if he’s an unrestricted free agent...
More Stories