Road to Recovery: Rebuilding I-85 bridge a complex process


Rebuilding a bridge isn’t as simple as snapping together pieces like an oversized Lego set. Building one fast is even more complicated.

Georgia Department of Transportation engineers began designing fixes for 700-feet of the I-85 bridge the night a fire caused a portion of it to collapse and badly damaged other sections.

IN-DEPTH: Is MARTA ready for its close-up after bridge collapse?

EXCLUSIVE: Who’s to blame for the I-85 collapse?

Marietta contractor C.W. Matthews Co., which will be paid up to $16.5 million to complete the project, started putting together cost estimates that same night. The bridge went up in flames on March 30 after a homeless man allegedly set fire to an upholstered chair, which then ignited several tons of coiled plastic conduit that had been stored underneath.

An indication of how quickly both shops were working: amounts for each of the 92 line items that make up the budget are written by hand. The Atlanta Journal-Constitution and Channel 2 Action News obtained the contract this week through a Georgia Open Records Act request.

“That’s unique; we hadn’t done that in a long time,” C.W. Matthews President Dan Garcia said of the hand-written budget amounts. “Everything happened so quickly, we ended up doing it the old-fashioned way.”

The company’s bid for fixing the bridge was reduced to $11.9 million after a couple hours of negotiations with the state and Federal Highway Administration, Garcia said. That amount doesn’t include $1.6 million for demolition, or $3.1 million in incentives the company can earn by completing the project early.

The budgeted line items include $3 million for concrete beams; $2.4 million for grading; $1.7 million for fast-curing superstructure concrete; and $1.5 million for traffic control, which includes barricades, signs, fencing and police officers. The federal government is expected to pick up most of the cost of construction.

Major considerations in designing the repairs included the geology of the ground beneath the bridge; the weight of the bridge and vehicles expected to use it; how quickly the concrete cured to specifications needed for a highway bridge; and, perhaps most importantly, how fast the concrete beams could be manufactured.

They even took into account the number of axles on tractor trailers — which distribute the weight of the trucks’ load as they cross the bridge.

“Bridges, by their very nature, are quite complex to design,” said GDOT Construction Director Marc Mastronardi. “The art in it becomes understanding how to take all that information and how to synthesize it.”

The concrete on the columns supporting the bridge cured in 24 hours. The decking is a 72-hour mix. Normally, concrete decking takes 14-days to dry, said Garcia, whose company completed pouring the first of six decks on Wednesday.

COMMUTING: MARTA adds parking spaces

RELATED: Will Trump budget scuttle Atlanta transit projects?

“There are costs associated with expediting a project like this,” Garcia said. “You use different chemicals and additives to achieve strength in concrete faster. They are about 35 to 40 percent more expensive in a 24-hour mix.

“The beam supplier was critical for us to be able to complete the work more quickly. Standard Concrete (Products) produced all the beams right here in Atlanta, except the ones over Piedmont Road. They began casting the first beams on Monday after the fire.”

Dozens of C.W. Matthews’ employees have worked 24 hours a day to demolish the old bridge and build the new one. Last week, the company had 45 people working at night and 40 during the day. GDOT has four to six inspectors working beside them at all times.

“Our role is the quality assurance piece,” Mastronardi said. “We have staff that are subject-matter experts in bridge construction.”

A stroke of luck that made design and construction easier: The foundation and 13 columns supporting the old bridge were still usable. Mastronardi said that probably saved a month of construction time.

The first step in building the new bridge was shoring up those original columns with more steel and concrete. Next, workers placed reinforced concrete caps over the columns to support 61 concrete beams — each one weighing about 80,000 pounds.

The beams themselves were laid on the caps and tied together for stability. Metal forms are placed to hold the concrete of the bridge deck.

After the decks are poured, they will be tested for smoothness and ground down if necessary. Then they’ll be grooved to prevent them from becoming slick when it rains. Finally, they’ll be striped, and workers will pour the concrete barrier walls on each side of the bridge deck.

GDOT officials said they believe construction will likely be done ahead of schedule before the June 15 deadline.

“Those (barriers) will be a sure sign we’re in the home stretch,” Mastronardi said.



Reader Comments ...


Next Up in Local

2 accused of ‘willful killing’ of foster teen found in Atlanta street
2 accused of ‘willful killing’ of foster teen found in Atlanta street

Two men accused of shooting a teenager who was in foster care and leaving her dead in an Atlanta street are in the DeKalb County jail on aggravated assault charges in a separate attempted armed robbery case.  Police believe slain 17-year-old Dennetta Franks may have been involved in the Sept. 19 armed robbery with her accused shooters, Wayne...
Streets named for the Confederacy in Atlanta to be renamed
Streets named for the Confederacy in Atlanta to be renamed

Atlanta streets named for some of the Confederacy’s most recognizable generals and leaders will likely be renamed in the coming weeks, Mayor Kasim Reed is expected to announce as early as today. What names might replace them is unclear, as are plans for other streets, monuments and markers named for rebels, according to a new report by a select...
3 metro Atlantans named ‘Southerners of the Year’
3 metro Atlantans named ‘Southerners of the Year’

Three Georgians — all metro Atlantans — have been named in a list of 60 Southerners who make Southern Living “proud to call this region home.”  Abiodun Henderson, Clarkston Mayor Edward “Ted” Terry and Marian Liou were included as “Southerners of the Year.&rdquo...
‘Not like the movies’: Inside the search for a missing Gwinnett man
‘Not like the movies’: Inside the search for a missing Gwinnett man

On this day, Tracy Sargent and her K-9s are searching for a Lawrenceville man who disappeared more than a year ago in a drug-induced rage. Over the last quarter-century — across the country and around the world — Sargent’s Georgia-based investigation team has helped track good guys and bad, missing persons and escaped convicts...
JUST IN: $7K reward issued in Barcelona Wine Bar manager’s death
JUST IN: $7K reward issued in Barcelona Wine Bar manager’s death

A $7,000 reward is being offered in the particularly heinous shooting of an Atlanta restaurant manager Sunday, police said. Chelsea Beller of Atlanta was forced upstairs to open a safe during a robbery by three men at Barcelona Wine Bar on Howell Mill Road, The Atlanta Journal-Constitution previously reported. The rest of the employees were tied up...
More Stories